Ireland must deliver 1GW of offshore wind by 2025 to meet 5GW target by 2030

Ireland needs to install 1GW of offshore wind energy capacity by 2025 if it is to meet the new government’s target of 5GW of installed offshore wind by 2030, a leading renewable energy developer said today.

Paul Cooley, Director of Capital Projects at SSE Renewables, told today’s Energy Ireland ‘Offshore Energy Conference’ that the new Coalition Government’s ambition to deliver an increased 5GW of offshore wind energy off Ireland’s eastern and southern coasts by the end of the decade is welcome, but said this new scale must be delivered at pace and with immediate effect if targets are to be met.

Delivery of 1GW of offshore wind energy in the Irish Sea by 2025 will get Ireland on track to meet the new 5GW target. It will also contribute 2 per cent of the Programme for Government’s annual 7 per cent reduction in Ireland’s overall greenhouse gas emissions between now and 2030. Completion of the 520MW Arklow Bank Wind Park by SSE Renewables in the next five years will itself directly contribute to just over half the 2 per cent reduction in carbon emissions that can be achieved by 2025.

In June 2020 SSE Renewables selected Arklow Harbour on Ireland’s East Coast as the preferred location for the Operations and Maintenance Base for Arklow Bank Wind Park, which will be home to 80 full-time employees once the project enters operation.

SSE Renewables’ Paul Cooley said:

“The new Government’s commitment to increased offshore wind energy ambition by 2030 is welcome but if Ireland is going to deliver 5GW of installed offshore capacity by the end of the decade, then Ireland needs to be delivering 1GW of new offshore wind by 2025 to get us on track.

“Installing operational offshore wind farms in the Irish Sea by the middle of the decade and within the lifetime of this Government will be vital in maintaining the momentum for offshore wind energy initiated by last year’s Climate Action Plan and further committed to in the new Coalition’s Programme for Government.

This is especially crucial if we are to establish an offshore wind energy industry in Ireland, including the development of an indigenous, job-creating supply chain.”

Paul Cooley said international market confidence in Ireland’s readiness to exploit offshore wind energy will be undermined by any perceived lack of urgency in developing the emerging energy sector here.

Paul Cooley added:

“Ireland will need to compete in a highly-competitive global offshore energy marketplace if it is going to achieve the country’s new 5GW offshore ambition. Action is needed now if we are going to deliver the revolution in renewables promised in the Programme for Government.

The commitment in the Programme to a first RESS auction for offshore wind in 2021 is hugely welcome. This auction must be delivered on time alongside the necessary grid connections policy to safeguard developer and market confidence that Ireland is finally open for business for offshore wind energy.

“Government and Industry must collaborate strategically to achieve the new Programme for Government targets, and ensure we gain real momentum in the delivery of new offshore wind capacity by 2025 and 2030.

In doing so we can outperform the 5GW target set for 2030, and finally begin exploiting the vast offshore wind resource around our island, establishing Ireland as a European and world leader in offshore wind energy.”

SSE Renewables is significantly progressed in plans to develop the next phase of the 520MW Arklow Bank Wind Park. It is targeting a delivery date of 2025 to meet Ireland’s interim target of 1GW of offshore wind energy in the same year, as committed to in Ireland’s Climate Action Plan.

When complete, the wind farm is expected to power around half a million homes each year with green energy, offsetting around 600,000 tonnes of carbon emissions or a 1% reduction in Ireland’s annual carbon emissions.

In June 2020 SSE Renewables selected Arklow Harbour on Ireland’s East Coast as the preferred location for the Operations and Maintenance Base for Arklow Bank Wind Park, which will be home to 80 full-time employees once the project enters operation.

Irish Tech News

Recent Posts

Could Digital Insurance Solve Food Security For Venezuela?

By David Stephen who looks at the idea of Digital Insurance and how it could…

2 hours ago

The Spider Awards 2026 Shortlist Announced as Record Entries Mark 29th Anniversary

The Spider Awards, Ireland’s longest-running and most prestigious digital awards ceremony, is proud to announce…

20 hours ago

NBI end of year update: over 450,000 homes, farms and businesses now ready to connect under the National Broadband Plan

National Broadband Ireland (NBI), the company responsible for delivering the Government’s National Broadband Plan (NBP),…

21 hours ago

UGREEN 200W GaN Desktop Charger Review

UGREEN has expanded its range of products that come with 3-pin plugs, suitable for the…

23 hours ago

Is smart dental tech worth the cost?

Smart toothbrushes have gone from novelty gadgets to genuinely sophisticated pieces of technology. They now…

23 hours ago

More about Irish Tech News


Irish Tech News are Ireland’s No. 1 Online Tech Publication and often Ireland’s No.1 Tech Podcast too.


You can find hundreds of fantastic previous episodes and subscribe using whatever platform you like via our Anchor.fm page here: https://anchor.fm/irish-tech-news


If you’d like to be featured in an upcoming Podcast email us at Simon@IrishTechNews.ie now to discuss.


Irish Tech News have a range of services available to help promote your business. Why not drop us a line at Info@IrishTechNews.ie now to find out more about how we can help you reach our audience.


You can also find and follow us on Twitter, LinkedIn, Facebook, Instagram, TikTok and Snapchat.